Based on the reading, scope creep is the agreement that limit the extent or scope of a project before starting the project. When the conflict happened, it can be carried out as what concluded in the terms.

The professor takes his friend as an example. His friend runs a construction company. He got a business recently to build fence for a woman. They come to an agreement with the work and price in verbal. Before he finished the job, the woman come up with that she need the fence painted white. His friend argued that he was responsible for the building rather than painting. In the end, his friend compromised on painting without any extra money.